Western Railway Announces 35-Day Mega Block for 6th Line Work Between Goregaon and Kandivali

Western Railway Announces 35-Day Mega Block for 6th Line Work Between Goregaon and Kandivali

In a significant move to enhance the railway infrastructure in Mumbai, the Western Railway (WR) is set to commence work on the 6th line between Goregaon and Kandivali. This project, which spans approximately 4.5 Kilometers, is scheduled to begin during the night of August 27/28, 2024, and is expected to be completed by October 5/6, 2024. The initiative aims to improve the capacity and efficiency of suburban train services in one of the busiest rail corridors in the city.

Project Details

The construction of the 6th line is part of a broader effort by the Western Railway to alleviate congestion and enhance the overall commuting experience for passengers. According to Shri Vineet Abhishek, Chief Public Relations Officer of Western Railway, the work will be executed over a period of 35 days, primarily during weekends to minimize disruption to daily commuters. The project will involve five major blocks, each lasting 10 hours, scheduled exclusively on Saturdays and Sundays. Notably, there will be no work conducted from September 11 to 17, 2024, in observance of the Ganpati Festival, ensuring that the festive spirit is not hampered by construction activities.

Mega Block Schedule and Impact on Services

To facilitate the construction, Western Railway has planned several mega blocks during which train services will be affected. The schedule is as follows:

  1. First Mega Block:
    • Date: August 31 - September 1, 2024
    • Duration: 10 hours
    • Impact: Approximately 150 suburban cancellations, 60 short-terminations, and delays of 50-60 minutes.
  2. Second Mega Block:
    • Date: September 7–8, 2024
    • Duration: 10 hours
    • Impact: Similar to the first block with approximately 150 suburban cancellations and delays.
  3. Third Mega Block:
    • Date: September 21 - 22, 2024
    • Duration: 10 hours
    • Impact: Increased disruptions with 180 suburban cancellations and delays.
  4. Fourth Mega Block:
    • Date: September 28 - 29, 2024
    • Duration: 10 hours
    • Impact: Up to 200 suburban cancellations and extended delays.
  5. Fifth Mega Block:
    • Date: October 5 - 6, 2024
    • Duration: 10 hours
    • Impact: 100 suburban cancellations and delays of 60-70 minutes.

During these mega blocks, approximately 20-22 long-distance trains will also experience delays of 15-20 minutes. Additionally, from September 28-29, non-interlocking work will be carried out on the 5th line between Goregaon and Kandivali, causing further delays for trains originating from Bandra Terminus.

Significance of the 6th Line

The addition of the 6th line between Goregaon and Kandivali is crucial for several reasons:

  • Increased Line Capacity: This expansion will significantly enhance the line capacity of the Mumbai suburban section, allowing for more trains to operate efficiently.
  • Reduced Congestion: By easing congestion on the existing tracks, the new line will help improve the punctuality of trains, making commutes smoother for passengers.
  • Segregation of Train Services: The project will facilitate the segregation of mainline trains from suburban services, allowing for dedicated paths for each, which is essential for maintaining schedules.
  • Enhanced Connectivity: Once completed, the 6th line will provide additional paths for running more trains, benefiting commuters traveling between Andheri, Borivali, and Virar.

Yatri - City Travel Guide

As the official local app for Mumbai, the Yatri app is designed to revolutionize your commuting experience. With real-time updates, seamless ticket booking, and accurate route planning, Yatri empowers millions of daily passengers to navigate the bustling Mumbai railway network with ease. Our user-friendly interface provides instant information on train schedules, delays, and platform changes, ensuring you stay informed at all times. Whether you're a seasoned commuter or a first-time traveler, Yatri - City Travel Guide is your reliable partner in making every journey smooth and efficient. 

Impact on Train Services

While the construction is underway, passengers should be prepared for some disruptions. A few long-distance trains will experience delays of approximately 15 to 20 minutes, and suburban services will see an average of 100 to 140 train cancellations and around 40 short-terminated services on weekends. Additionally, from September 28-29, non-interlocking work will be carried out on the 5th line between Goregaon and Kandivali, causing further delays for trains originating from Bandra Terminus.

Transforming Mumbai's Railway Landscape

As the sun sets on the bustling city of Mumbai, a new dawn breaks for its commuters. The commencement of the 6th line work between Goregaon and Kandivali marks a pivotal moment in the history of the city's railway infrastructure. Like a well-oiled machine, Western Railway is poised to transform the way millions of Mumbaikars navigate their daily lives.

By enhancing capacity, reducing congestion, and segregating train services, this project promises to usher in a new era of efficiency and reliability. Imagine a world where your commute is no longer a test of endurance, but a seamless journey filled with the promise of punctuality and comfort. This is the future that Western Railway is committed to delivering, one that will forever change the way we think about public transportation in Mumbai.

As the project progresses, passengers are encouraged to stay informed about train schedules and potential disruptions. It's a small price to pay for the greater good, for the dedication to upgrading the railway network will ultimately lead to a more efficient and reliable service for all commuters in the region. So, let's embrace the challenges ahead, knowing that the light at the end of the tunnel is a brighter, more connected future for our beloved city.

Dated August 29, 2024